In planning, unstable requirements typically lead to which effect on the program?

Study for the PMT4810 Preventive Medicine (PM) Practitioner Certification Exam. Enhance your knowledge with multiple choice questions and detailed explanations. Prepare thoroughly and boost your confidence for the exam!

Multiple Choice

In planning, unstable requirements typically lead to which effect on the program?

Explanation:
Unstable requirements introduce frequent change and ambiguity into planning. When the scope keeps shifting, the team must continually rework design, code, and tests, which drives extra labor and delays. Estimates become less reliable, so the schedule becomes longer and costs rise, while risk grows because of increased chances of rework, bugs, and integration issues. Shorter development cycles require a stable understanding of what’s being built, so instability tends to lengthen cycles rather than shorten them. Immediate cost reductions aren’t expected; changes and rework add expense rather than cut it. The overall effect is a negative impact on both cost and schedule, with higher uncertainty and risk.

Unstable requirements introduce frequent change and ambiguity into planning. When the scope keeps shifting, the team must continually rework design, code, and tests, which drives extra labor and delays. Estimates become less reliable, so the schedule becomes longer and costs rise, while risk grows because of increased chances of rework, bugs, and integration issues. Shorter development cycles require a stable understanding of what’s being built, so instability tends to lengthen cycles rather than shorten them. Immediate cost reductions aren’t expected; changes and rework add expense rather than cut it. The overall effect is a negative impact on both cost and schedule, with higher uncertainty and risk.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy